Rural Carson County in the Texas Panhandle (photo by Carol M. Highsmith, Library of Congress). Source: Wikimedia Commons (Part of a large wind farm in rural Carson County in the Texas panhandle LCCN2014633726.tif). License: Public domain.
Quick Answer: Fermi’s Project Matador, a planned AI data center and private power campus on more than 5,000 acres of Texas Tech University System land near Amarillo, has its first signed tenant commitment: a preliminary 600 MW agreement with an unnamed investment-grade hyperscaler that includes a $200 million prepayment. The company has no revenue yet, reported a third-quarter 2026 net loss of $141.6 million and now targets first power in late second quarter or early third quarter of 2027.
Few Texas data center projects have been as ambitious, or as closely watched, as Fermi’s Project Matador in Carson County. The company, which trades on Nasdaq under the ticker FRMI, wants to build a private grid of natural gas, nuclear, solar and battery power in the Texas Panhandle and sell powered capacity to AI computing customers. On November 12, 2026, Fermi reported its third-quarter results and announced new agreements with a hyperscale customer. This report lays out where the site, the permits, the nuclear license, the water supply and the finances stand.
What is Project Matador?
Project Matador is Fermi’s planned campus on land leased from the Texas Tech University System (TTUS) under a 99-year lease. The site sits next to the U.S. Department of Energy’s Pantex Plant, about 150 miles north of Lubbock near Amarillo. Fermi describes the site as more than 5,000 acres; its Nuclear Regulatory Commission (NRC) application specifies 5,855 acres.
The design is a behind-the-meter private grid that would combine combined-cycle natural gas generation, a nuclear complex, utility grid power, solar and battery storage, and would deliver that power directly to data center buildings on site. Rather than waiting in a utility interconnection queue, tenants would buy power and space from Fermi’s own system.
| Developer | Fermi (Nasdaq: FRMI) |
| Location | Carson County, near Amarillo, adjacent to DOE’s Pantex Plant |
| Land | More than 5,000 acres (5,855 acres in NRC filing), 99-year TTUS lease |
| Planned power | Up to about 17 GW, contingent on customer agreements |
| Gas permit | TCEQ approval Feb. 25, 2026 for 93 turbines (more than 5 GW) |
| Nuclear plan | Four Westinghouse AP1000 reactors, about 4.4 GW; license under NRC review |
| Water | Up to 2.5 million gallons per day of City of Amarillo groundwater |
| First tenant commitment | Preliminary 600 MW hyperscaler deal with $200M prepayment (Nov. 2026) |
| First power target | Late Q2 or early Q3 2027 |
| CEO | Lee McIntire (since Aug. 11, 2026) |
How much power does Fermi plan to build?
The target has grown over time. Earlier plans called for 11 GW in total, including 4.4 GW of nuclear power from four Westinghouse AP1000 reactors of about 1.1 GW each. In a March 27, 2026 release, Fermi raised the target to about 17 GW: roughly 11 GW of natural gas plus 4.4 GW of nuclear, with solar and battery storage also in the mix.
Fermi’s third-quarter release ties that figure to customer demand. It says Matador is expected to ramp to about 17 GW if binding customer agreements are signed, and that any capacity above about 6 GW will require additional permits, financing, interconnection and land. On the third-quarter call, CEO Lee McIntire cited 2.2 GW of current capacity and said Fermi had secured more than 2 GW of generation equipment. In March, the company said it had secured assets for about 2.5 GW of combined-cycle gas generation.
| Source | Planned Capacity | Status |
|---|---|---|
| Natural gas | About 11 GW | More than 5 GW approved by TCEQ (Feb. 2026); second 5 GW application filed March 2026 |
| Nuclear | 4 AP1000 units, about 4.4 GW | Combined license application under NRC review; Final EIS targeted Dec. 2026 |
| Solar and battery storage | Included in plan; no breakdown published | Not specified |
| Utility grid | Not quantified | Part of private grid design |
| Total | 11 GW earlier; about 17 GW now | Above about 6 GW requires more permits, financing and land |
What permits has Fermi received?
Is the natural gas plant permitted?
On February 25, 2026, the Texas Commission on Environmental Quality (TCEQ) approved an air permit for 93 natural gas turbines, allowing more than 5 GW of gas-fired generation, E&E News reported. E&E noted that Matador alone would be larger than any existing U.S. fossil fuel power plant, and that nearby residents had raised environmental concerns. Fermi refers to the approval as its roughly 6 GW permit. On March 27, 2026, Fermi filed a second air permit application with TCEQ for an additional 5 GW.
Where does the nuclear license stand?
Fermi America, LLC filed a combined license application with the NRC for four AP1000 units, which the agency lists as Project Matador Nuclear Units 1 through 4. Part 1 was filed on June 17, 2025, and a revised Part 2 on August 20, 2025. The NRC completed its acceptance review and docketed both parts on September 5, 2025.
The NRC issued a Draft Environmental Impact Statement on September 30, 2026, followed by a 45-day comment period, and is targeting a Final Environmental Impact Statement for December 2026. The safety evaluation schedule and the licensing decision date are listed as to be determined. Part 3, including siting material, is targeted for October 31, 2027, with a full acceptance review targeted for December 15, 2027. According to Lubbock Lights, the NRC application projects more than 9,000 peak construction jobs and more than 600 permanent jobs for the nuclear portion alone, and an earlier plan targeted the first AP1000 operating by April 2031.
Who is Fermi’s first tenant?
Tenant commitments have been the project’s biggest test. In December 2025, an unnamed first tenant withdrew from a non-binding deal that had included a $150 million advance. In August 2026, Fermi signed a lease with TensorWave; the third-quarter release says that lease was terminated, along with a related AMD credit support agreement.
On November 12, 2026, Fermi announced new agreements with an unnamed investment-grade hyperscaler. Under the preliminary terms, the hyperscaler advances a 600 MW deployment beginning in 2027. The agreements include a $200 million prepayment, due to be wired in full by November 13, and a $15 million site development agreement. A $90 million agreement covering steel and building materials was still being finalized. A definitive lease is still being negotiated.
On the earnings call, Fermi said the deal covers up to eight buildings and that it wants four to five anchor hyperscalers over time. The company said it aimed to begin mobilizing on site by December 1. Fermi cites a “Powered Land+” benchmark of $3.9 million to $5.1 million per MW for the type of capacity it is offering.
What do Fermi’s financial results show?
Fermi is still a pre-revenue company. For the third quarter ended September 30, 2026, it reported:
- A net loss of $141.6 million, or $0.22 per share, and a nine-month net loss of $356.1 million.
- General and administrative expenses of $142.2 million, including $65.8 million of stock-based compensation.
- Capital spending of $133.4 million, down from about $185 million in the second quarter, and $759.5 million for the first nine months.
- Net property, plant and equipment of about $1.67 billion and total assets of $2.10 billion.
- Cash of $315.5 million and net debt of $958.4 million.
- 646,138,173 shares outstanding.
Fermi closed $430 million of convertible notes in July 2026, and an amendment to its turbine warehouse financing facility cost about $25 million in fees, according to the earnings call summary.
| Measure | Q3 2026 | Nine Months 2026 |
|---|---|---|
| Revenue | None | None |
| Net loss | $141.6M ($0.22/share) | $356.1M |
| Capital spending | $133.4M | $759.5M |
| Cash (Sept. 30) | $315.5M | n/a |
| Net debt (Sept. 30) | $958.4M | n/a |
| Net PP&E | About $1.67B | n/a |
| Total assets | $2.10B | n/a |
How did the IPO go?
Fermi priced its initial public offering on September 30, 2025, selling 32.5 million shares at $21 each, with an option for 4.875 million more, about $682.5 million in gross proceeds. Shares began trading on the Nasdaq Global Select Market on October 1, 2025, and on the London Stock Exchange the next day. UBS, Evercore ISI, Cantor and Mizuho led the offering. The stock closed its first day at $32.50, according to Lubbock Lights. Fortune reported that the company’s market value was nearly $20 billion at the IPO and about $3.4 billion by April 20, 2026.
How will the campus get water?
Fermi, Inc. has a water supply agreement with the City of Amarillo for up to 2.5 million gallons a day of groundwater. The agreement runs 20 years with two optional 10-year renewals, and Fermi pays twice the in-city rate. Fermi must build two wells in the city’s Carson County Well Field, along with piping and a backup generator, by January 2027 and transfer them to the city. The agreement excludes effluent from the city’s Hollywood Road Wastewater Treatment Plant.
Who is leading Fermi?
The company has gone through a leadership change in 2026. Co-founder Toby Neugebauer left the executive role in April and remains on the board, and the chief financial officer also resigned, Fortune reported. Fortune also reported that the headquarters is moving from Amarillo to Dallas. Lee McIntire became chief executive on August 11, 2026. He is a former Bechtel executive vice president, a former CEO of CH2M Hill and CEO of TerraPower from 2015 to 2018. Marius Haas is chairman, and former Texas Gov. Rick Perry is a co-founder.
Fermi said in its third-quarter release that it is still working with TTUS on lease conditions that must be met before vertical construction begins, and that TTUS Chancellor Brandon Creighton reaffirmed the partnership the week of November 12. Expanding the total acreage depends on pending land purchases.
What is the project timeline so far?
| Date | Event |
|---|---|
| June 17, 2025 | NRC combined license application Part 1 filed |
| Sept. 5, 2025 | NRC dockets Parts 1 and 2 |
| Sept. 30-Oct. 1, 2025 | IPO priced at $21; trading begins on Nasdaq |
| December 2025 | First prospective tenant withdraws from non-binding deal |
| Feb. 25, 2026 | TCEQ approves air permit for 93 gas turbines |
| March 27, 2026 | Second 5 GW air permit application; target raised to about 17 GW |
| April 2026 | Co-founder leaves executive role |
| July 2026 | $430 million convertible notes close |
| Aug. 11, 2026 | Lee McIntire becomes CEO |
| Sept. 30, 2026 | NRC issues Draft Environmental Impact Statement |
| Nov. 12, 2026 | Q3 results; preliminary 600 MW hyperscaler agreement |
| December 2026 | Final Environmental Impact Statement targeted |
| January 2027 | Water wells due to the City of Amarillo |
| Late Q2 / early Q3 2027 | First power target |
How is Fermi’s model different from other Texas data center campuses?
A data center campus that relies on a utility connection depends on that utility’s transmission upgrades and grid approvals. Fermi’s pitch is that it will generate its own power on site and sell space and electricity together, so its customers depend on Fermi’s construction schedule rather than a utility’s. That is why the company prices its offering against a “Powered Land+” benchmark of $3.9 million to $5.1 million per MW and why its permit filings are for power plants as much as for buildings.
The model also concentrates risk. Fermi must finance and build generation, buildings, water infrastructure and, eventually, nuclear reactors at the same time, before it has revenue. The company’s own release makes growth beyond about 6 GW conditional on more permits, financing, interconnection and land. The 600 MW preliminary agreement is about one-tenth of that first 6 GW tier, and roughly 3.5% of the 17 GW long-range target, by our calculation.
For the Panhandle, the stakes are large. The nuclear portion alone projects more than 9,000 peak construction jobs and more than 600 permanent jobs, and the water agreement makes Fermi a significant new customer for the City of Amarillo’s Carson County well field.
What should the Texas data center industry watch?
- The definitive lease. Converting the preliminary 600 MW agreement into a binding lease is the most important near-term milestone.
- Site mobilization. Fermi aimed to begin mobilizing by December 1, 2026, and must finish its water wells by January 2027.
- First power. The target is late second quarter or early third quarter of 2027. An earlier plan reported by Lubbock Lights called for about 1 GW from six Siemens SGT-800 turbines by the end of 2026.
- NRC schedule. The Final Environmental Impact Statement is targeted for December 2026.
- Second gas permit. The 5 GW TCEQ application filed in March 2026 is required for growth beyond about 6 GW.
- Liquidity. With $315.5 million in cash at September 30 and quarterly capital spending above $130 million, the $200 million prepayment and future financing will be closely watched.
Frequently Asked Questions
Where is Fermi’s Project Matador?
In Carson County in the Texas Panhandle, near Amarillo and next to DOE’s Pantex Plant, on Texas Tech University System land.
How much power will Project Matador have?
Fermi targets about 17 GW if binding customer agreements are signed, including about 11 GW of gas and 4.4 GW of nuclear. Growth above about 6 GW needs more permits, financing and land.
Does Fermi have a tenant?
It has a preliminary 600 MW agreement with an unnamed investment-grade hyperscaler, including a $200 million prepayment. A definitive lease is still being negotiated.
When will the campus produce power?
Fermi now targets first power in late second quarter or early third quarter of 2027.
Is the nuclear plant approved?
No. The NRC is reviewing Fermi’s combined license application for four AP1000 reactors; the licensing decision date has not been set.
Sources and Further Reading
- Fermi Announces New Agreements with Investment-Grade Hyperscaler and Third Quarter 2026 Financial Results – Fermi
- Fermi Q3 Earnings Call Highlights – MarketBeat
- Fermi America Combined License Application, Units 1-4 – U.S. Nuclear Regulatory Commission
- Fermi America Announces Pricing of Initial Public Offering – Fermi America
- Fermi America Files Second Clean Air Permit Application with TCEQ – Fermi America
- Texas Approves Data Center Behemoth’s Massive Gas Power Play – E&E News
- Water Supply Agreement, City of Amarillo and Fermi, Inc. – City of Amarillo
- Texas Tech, Fermi Team Up on Project Matador – Lubbock Lights
- Fermi Names Lee McIntire as Chief Executive Officer – Fermi
- Financially Struggling AI Power Startup Fermi Loses CEO – Fortune