Quick Answer: Houston is still a small data center market by Texas standards, but it is changing quickly. JLL counted 287 MW of operating capacity and 390 MW under construction at midyear 2026. CBRE has flagged elevated vacancy in the existing colocation stock, while CenterPoint Energy is lining up roughly 14 GW of large-load projects, mostly data centers, for grid connection by 2030.
Houston’s data center market has long served energy companies, hospitals and corporate tenants. Brokerage reports, utility filings and state construction registrations from 2025 and 2026 show it moving into hyperscale development, with large campuses planned on the metro’s western and southwestern edges.
How big is the Houston data center market today?
How big depends on whose count you use, and the two largest brokerage houses measure the market differently.
CBRE’s North America Data Center Trends report for the second half of 2025, as summarized by EnergyCapitalHTX in March 2026, put Houston’s inventory at 154 MW. That was roughly flat against the second half of 2024. CBRE counted 28.5 MW under construction and said Houston’s capacity could more than double by the end of 2028.
JLL’s midyear 2026 North America report, as summarized by EnergyCapitalHTX in August 2026, gives much higher figures. JLL counted 287 MW of operational capacity in Houston and 390 MW under construction, and it recorded 25 MW of net absorption in the first half of 2026. Even so, JLL ranked Houston well behind Dallas-Fort Worth, Austin-San Antonio and West Texas in operating capacity.
The brokerages measure the market differently, so the two sets of numbers should not be compared line by line. Both show a modest existing base and a large pipeline relative to it.
| Measure | Figure | Source and period |
|---|---|---|
| Inventory | 154 MW | CBRE, H2 2025 |
| Under construction | 28.5 MW | CBRE, H2 2025 |
| Vacancy | 19.7% | CBRE, H1 2025 |
| Operational capacity | 287 MW | JLL, midyear 2026 |
| Under construction | 390 MW | JLL, midyear 2026 |
| Net absorption | 25 MW | JLL, H1 2026 |
| Facilities listed | 59 data centers, 36 operators | Data Center Map, via EnergyCapitalHTX, March 2026 |
| CenterPoint large-load projects expected eligible | About 14 GW | CenterPoint Q2 2026 call, via Utility Dive |
How does Houston compare with other Texas markets by facility count?
Data Center Map, a directory cited by EnergyCapitalHTX, listed 59 data centers in the Houston area run by 36 operators. By the same count, Dallas-Fort Worth had more than 180, San Antonio more than 50, Austin about 40, and Texas as a whole more than 400. Named Houston operators include DataBank, Data Foundry, Digital Realty, IBM, Logix Fiber Networks, Lumen and TRG Datacenters.
Statewide, JLL reported 26 GW of existing and under-construction capacity at midyear 2026, the most of any state, so Houston’s share remains small.
What is Houston’s data center vacancy rate?
Houston is unusual among U.S. markets because it has had real vacancy. CBRE’s first-half 2025 Houston market profile put vacancy at 19.7%. CBRE said the rate rose after one operator delivered new space, and it noted that second-generation and legacy space was coming back to the market. In its second-half 2025 data, CBRE again described Houston as having “elevated vacancy and uneven absorption,” according to EnergyCapitalHTX.
That is far from the national picture. CBRE’s North America Data Center Trends H1 2026 report, published August 27, 2026, put vacancy across its primary markets at a record-low 1.4%. JLL reported North American vacancy of about 1% for a third straight year. Houston is not one of the eight primary markets in CBRE’s main report.
Why has Houston had more vacancy than other markets?
The CBRE profile points to the market’s makeup. Houston’s colocation base was built mainly for enterprise users, and CBRE cited continued demand from the oil and gas sector. In a market this size, one unleased delivery moves vacancy sharply. Hyperscale capacity in markets such as Dallas-Fort Worth is mostly pre-committed before it is built. JLL said about 95% of the 66 GW under construction across North America was pre-committed.
What do Houston data centers cost to lease?
The public summaries of the CBRE and JLL reports reviewed for this article do not include Houston asking rents. CBRE’s Houston profile shows average asking rates only in a chart, without published values. Houston tenants comparing quotes therefore have no public Houston benchmark from either firm.
The national trend does show which way pricing is moving. In its H1 2026 report, CBRE said average asking rates in its primary markets rose 8.3% for 3 MW to 10 MW requirements, 7.9% for 500 kW to 3 MW, 6.7% for deals over 10 MW, and 4.3% for 250 kW to 500 kW. JLL said North American rates have risen nearly 70% since 2020, an average of about 9% a year, and that it expects the pricing momentum to continue through 2030.
Which major campuses and operators are building in the Houston area?
Several projects disclosed in 2025 and 2026 account for most of the expected growth. They range from a 24 MW colocation expansion to a $1.2 billion hyperscale campus.
What is Serverfarm building in Houston’s Energy Corridor?
Serverfarm, a developer backed by Manulife Investment Management, announced on January 29, 2026, that it had closed a $3.0 billion credit facility in December 2025. A syndicate of 23 institutional lenders provided the facility, with TD Securities as administrative agent and joint lead arranger. One project the facility will fund is a 250-acre hyperscale campus in Houston’s Energy Corridor, with more than 500 MW of development potential and two on-site substations, according to the company’s release.
EnergyCapitalHTX, citing CoStar, reported that the campus and two other Serverfarm projects are leased to unnamed tenants. It also reported a 60 MW AI-ready Serverfarm facility under construction in the area, with an estimated cost of $137 million, 438,000 square feet, and completion targeted for the third quarter of 2027. Serverfarm says it uses closed-loop water cooling at all of its locations.
What is Amazon’s Project Eagle in Wharton County?
The largest proposal near Houston is Amazon’s. Amazon Data Services filed four project registrations with the Texas Department of Licensing and Regulation for “Project Eagle,” near Boling in Wharton County, about 60 miles southwest of Houston, BIC Magazine reported in July 2026. The site covers about 2,700 acres near FM 1301 and FM 442 along Eaglewood Road.
The four registered buildings, A through D, are 189,060 square feet each, with an estimated construction cost of $300 million per building. That comes to about 756,240 square feet and $1.2 billion. The buildings would occupy less than 1% of the property, BIC Magazine noted. The filings do not give a construction schedule.
What is TRG Datacenters adding in Spring?
TRG Datacenters broke ground on November 14, 2025, on HOU2, the second building on its campus at 2626 Spring Cypress Road in Spring. HOU2 will have 24 MW of utility capacity in 110,000 square feet, and TRG is targeting move-in-ready IT capacity as early as the fourth quarter of 2026. TRG said its first building, HOU1, delivered in 2018, is nearly fully subscribed, and that 16 carriers are already on the campus. CenterPoint Energy is listed as a project partner.
What does DataBank operate in West Houston?
DataBank entered Houston in 2022 when it agreed to buy CyrusOne’s four Texas data centers for $670 million, according to DatacenterDynamics. The deal covered CyrusOne’s entire Houston footprint, including buildings on the Westway Park Boulevard campus. DataBank now plans a 3.15 MW rooftop solar array at HOU3, its 162,000-square-foot building at 11003 Corporate Centre Drive in Westway Park, according to Energy Digital.
Which other projects are in the pipeline?
DatacenterDynamics reported in June 2026 that Dataprana had acquired two sites outside Houston totaling 92 MW. A Baxtel listing for the first site describes it as planned for 2027, with nearby substation infrastructure, fiber and natural gas access, and secured through the company’s Prana Energy land-and-power division.
In Brazoria County, Nightpeak Energy has proposed the Old Ocean Data Center on 158 acres near Sweeny, about 65 miles southwest of Houston, Bisnow reported in March 2026. The $3.5 billion plan calls for two 310 MW hyperscale data centers and two 310 MW combustion turbine plants, with the data center scheduled to begin energizing in 2027. County commissioners unanimously denied the developer’s requested tax abatements, and county officials said they had little authority to stop the project.
| Project | Location | Scale | Status / timing |
|---|---|---|---|
| Serverfarm hyperscale campus | Energy Corridor, Houston | 250 acres, 500+ MW potential | Funded by $3.0B facility closed Dec. 2025 |
| Serverfarm AI facility | Houston area | 60 MW, 438,000 sq ft, $137M | Target Q3 2027 |
| Amazon Project Eagle | Boling, Wharton County | 4 buildings, 756,240 sq ft, $1.2B | Registered with TDLR; no public schedule |
| TRG HOU2 | Spring | 24 MW, 110,000 sq ft | Capacity as early as Q4 2026 |
| Nightpeak Old Ocean | Near Sweeny, Brazoria County | 2 x 310 MW data centers, $3.5B with power plants | Energizing from 2027 per developer |
| Dataprana sites | Outside Houston | Two sites, 92 MW combined | First site planned 2027 |
Where in the Houston region are data centers being built?
The existing cluster sits on the west side, at Westway Park and in the Energy Corridor. New large-scale projects are moving farther out. EnergyCapitalHTX reported that JLL sees developers evaluating West Houston and nearby areas for large campuses because power is accessible there, flood risk is lower, and behind-the-meter power is an option.
JLL describes Houston as shifting from an enterprise colocation market toward what it calls a “credible large-scale growth market.” It notes that corporate, energy and healthcare users remain active while cloud and technology tenants grow.
How much power is available for data centers on CenterPoint’s system?
Power is where Houston’s figures are largest. CenterPoint Energy Houston Electric serves about 2.8 million metered customers. On its second-quarter 2026 earnings call, CenterPoint said it had submitted more than 17 GW of large-load projects to ERCOT for “Batch Zero,” the first group studied under the large-load interconnection rules Texas regulators approved in June 2026, Utility Dive reported.
CenterPoint expects about 14 GW of that to be eligible: roughly 10 GW as base load with all required ERCOT studies approved, and about 4 GW as studied load. Another 3 GW awaits study approval. CenterPoint said the 14 GW is backed by signed facility extension agreements and about $900 million in customer cash commitments and deposits.
How does the large-load queue compare with Houston’s current demand?
The 14 GW is more than 65% above the Houston area’s current peak demand of 21 GW. CEO Jason Wells said CenterPoint expects “nearly all of these projects to be energized by the end of 2030.” The company expects 50% load growth by the end of 2029 and about 2 GW of additional distribution-level demand over the next several years.
Earlier in 2026, Rigzone reported that CenterPoint was planning for about 8 GW of data center load in Greater Houston by 2029, with about 3.5 GW of it under construction. CenterPoint also reported 12.2 GW of firmly committed industrial load and projected that peak demand in its Houston Electric territory would exceed 30 GW by 2029, nearly 50% above 2024.
| CenterPoint metric | Figure |
|---|---|
| Large-load projects submitted for Batch Zero | More than 17 GW |
| Expected eligible (base + studied) | About 14 GW (10 GW + 4 GW) |
| Customer cash commitments and deposits | About $900 million |
| Current Houston-area peak demand | 21 GW |
| Projected peak demand by 2029 | Over 30 GW |
| 10-year capital plan (through 2035) | $66.7 billion |
What is CenterPoint spending to serve the new load?
In July 2026, CenterPoint raised its 10-year capital plan by $1.2 billion to $66.7 billion through 2035, citing large-load demand in Houston and higher costs for its Downtown Houston Revitalization project. CenterPoint said the new large loads should produce more than $5 billion in savings for residential and commercial customers over the next decade, as fixed grid costs are spread across more usage.
Frequently Asked Questions
How many data centers are in the Houston area?
Data Center Map lists 59 data centers in the Houston area run by 36 operators, according to EnergyCapitalHTX. Operators include DataBank, Data Foundry, Digital Realty, IBM, Lumen and TRG Datacenters.
Is Houston’s data center vacancy higher than the national average?
Yes. CBRE reported 19.7% vacancy in Houston in the first half of 2025 and described vacancy as elevated in late 2025. National vacancy is about 1% to 1.4%, according to JLL and CBRE.
What is the largest proposed data center campus near Houston?
Amazon’s Project Eagle near Boling in Wharton County covers about 2,700 acres. Its first four registered buildings total about 756,240 square feet and an estimated $1.2 billion. Serverfarm’s 250-acre Energy Corridor campus has more than 500 MW of development potential.
Can CenterPoint supply power to new Houston data centers?
CenterPoint says about 14 GW of large-load projects are expected to be eligible in ERCOT’s first batch study under the new state rules, and it expects nearly all of them to be energized by the end of 2030. Individual project timing depends on ERCOT studies and grid upgrades.
Sources and Further Reading
- Houston data center capacity expected to double, CBRE report says (EnergyCapitalHTX)
- North America Data Center Trends H1 2025: Houston market profile (CBRE)
- North America Data Center Trends H1 2026 (CBRE)
- Data center demand exceeds expectations as H1 2026 absorption hits record 25 GW (JLL)
- Houston data centers coverage, including JLL midyear 2026 figures (EnergyCapitalHTX)
- CenterPoint Energy sees 14 GW of Texas Batch Zero large load (Utility Dive)
- CenterPoint Targets 8 GW of Data Center Load in 3 Years (Rigzone)
- Manulife IM-backed Serverfarm secures $3.0 billion credit facility (Serverfarm press release via Cision)
- Amazon data center plans advance near Boling, Texas (BIC Magazine)
- Breaking Ground on 24MW Houston Expansion (TRG Datacenters)
- DataBank’s plans for Houston’s largest rooftop solar array (Energy Digital)
- DataBank acquires four CyrusOne data centers in Texas for $670m (DatacenterDynamics)
- Houston-area county rejects tax break for $3.5B data center project (Bisnow)
- Houston news tag and Dataprana coverage (DatacenterDynamics); Dataprana Houston 1 listing (Baxtel)