Quick Answer: CBRE’s North America Data Center Trends H1 2026 report puts Dallas-Fort Worth colocation inventory at 1,432.8 MW, up about 65% in a year, with 39.6 MW available (roughly 2.8%) and more than 765 MW under construction, 95% of it preleased. JLL’s midyear 2026 report says Austin/San Antonio completed 1.7 GW and absorbed 796 MW in the first half. Across Texas, new capacity is mostly spoken for before it is finished.
As of November 2026, the latest full broker reports on Texas data centers cover the first half of the year. CBRE, JLL and Cushman & Wakefield count capacity differently, so their totals for the same metro can differ by a factor of three. All three agree that Dallas-Fort Worth is among North America’s largest markets, that the Austin-San Antonio corridor is growing fast, and that very little finished capacity in either metro is empty. Below are each firm’s figures and the named campuses that state construction filings show going up now.
How big is the Dallas-Fort Worth data center market in 2026?
CBRE released its North America Data Center Trends H1 2026 report on August 27, 2026. It counts 1,432.8 MW of colocation inventory in Dallas-Fort Worth at mid-year. That makes DFW the third-largest of CBRE’s eight primary markets, behind Northern Virginia (4,496.5 MW) and Atlanta (1,803.2 MW), and ahead of Phoenix, Chicago, Silicon Valley, Hillsboro and New York Tri-State. The eight markets total a record 10,903 MW, so DFW holds roughly 13% of all primary-market supply.
A year earlier, CBRE’s H1 2025 profile counted 869.5 MW, so DFW inventory grew about 65% in twelve months. CBRE’s full-year 2025 report said DFW had become the third North American market to pass 1 GW of supply.
What is the DFW data center vacancy rate?
CBRE reports 39.6 MW of available capacity in DFW at mid-2026. That is the largest block of open space in any primary market, but it is still small: 39.6 MW against 1,432.8 MW of inventory is a vacancy rate of about 2.8%. The national primary-market rate was 1.4%, a record low, and Northern Virginia’s was 0.2%. Only New York Tri-State and Silicon Valley had a higher share of space available.
| Primary market | Inventory (MW) | Available (MW) | Available as % of inventory |
|---|---|---|---|
| Northern Virginia | 4,496.5 | 10.8 | 0.2% |
| Atlanta | 1,803.2 | 29.5 | 1.6% |
| Dallas-Fort Worth | 1,432.8 | 39.6 | 2.8% |
| Phoenix | 1,069.2 | 12.1 | 1.1% |
| Chicago | 910.6 | 20.0 | 2.2% |
| Silicon Valley | 509.2 | 21.2 | 4.2% |
| Hillsboro, OR | 491.4 | 1.1 | 0.2% |
| New York Tri-State | 190.0 | 13.7 | 7.2% |
Source: CBRE, North America Data Center Trends H1 2026 (press release, August 27, 2026). The percentage column is calculated from CBRE’s inventory and availability figures.
How much data center capacity is under construction in DFW?
CBRE counts more than 765 MW under construction in DFW at mid-2026, and 95% of it is already preleased. In H1 2025 the figures were 425.1 MW under construction and 78% preleased, so the DFW pipeline grew by about 80% in a year while the share already leased went up. CBRE also tracks 3.7 GW of planned greenfield development in DFW that has not started construction. It notes that several large Fort Worth-area projects sit outside the 30-mile radius around Dallas’s Infomart interconnection hub, and that powered land prices are rising.
Across the eight primary markets, CBRE counts a record 7,481.1 MW under construction, up 24.8% from a year earlier, with 80.4% preleased. Atlanta, at about 2,882 MW, is now the largest construction market. Net absorption reached 1,456.2 MW, up 11.7%, and CBRE estimates less than 1,500 MW remains uncommitted, about six months of demand.
Why do JLL and CBRE report such different numbers for Dallas?
JLL’s North America Data Center Report – Midyear 2026, released August 11, 2026, measures a much larger DFW market. Its release says Dallas-Fort Worth delivered more than 2 GW in the first half and absorbed even more. Dallas Innovates reported JLL’s detailed DFW figures as 4,587 MW of existing inventory, 3,202 MW under construction, 2,164 MW delivered and 2,297 MW absorbed in the first half, with vacancy below 1%.
The firms are measuring different things. CBRE’s primary-market series tracks leasable colocation and wholesale capacity in a defined metro; JLL’s totals cover a wider geography and more hyperscale and self-build capacity. Readers comparing years should stay within one firm’s series.
| DFW metric (H1 2026) | CBRE | JLL |
|---|---|---|
| Existing inventory | 1,432.8 MW | 4,587 MW |
| Under construction | 765+ MW (95% preleased) | 3,202 MW |
| Vacancy | ~2.8% (39.6 MW available) | Under 1% |
| First-half deliveries | Not stated | 2,164 MW |
| First-half absorption | Not stated for DFW | 2,297 MW |
| Planned, not started | 3.7 GW greenfield | Not stated |
Source: CBRE, North America Data Center Trends H1 2026 (DFW chapter and August 27, 2026 release); JLL, North America Data Center Report – Midyear 2026 (August 11, 2026 release), with JLL’s detailed DFW figures as reported by Dallas Innovates, August 18, 2026.
Cushman & Wakefield ranks markets rather than sizing them in its headline releases. Its 2026 Global Data Center Market Comparison, released in May 2026, named Dallas the No. 1 primary data center market in the world for the first time, ahead of Atlanta, Virginia, Columbus and Johor, Malaysia. The same study put Austin-San Antonio first among secondary markets. Its Americas Data Center Update for H1 2026 counted 50.3 GW operational across the Americas, 37.7 GW under construction (91.7% precommitted) and 3.8% vacancy.
How much does data center space cost in Texas?
No firm published a DFW-only asking rate in text for H1 2026, but national figures show the direction. CBRE’s full-year 2025 report put the average North American lease rate at $194.95 per kW per month, up 6.5% from 2024 and the fourth straight annual increase. In H1 2026, CBRE says asking rates rose year over year for every deployment size:
- 3 MW to 10 MW: up 8.3%
- 500 kW to 3 MW: up 7.9%
- 10 MW and larger: up 6.7%
- 250 kW to 500 kW: up 4.3%
JLL says North American rents have risen nearly 70% since 2020, about 9% a year, and expects pricing to hold through 2030. Construction costs have stayed competitive: Dallas Innovates, citing Cushman & Wakefield’s prior-year cost guide, reported DFW building costs of about $9.4 million to $12.1 million per MW, tied with Austin for second-lowest of the 19 U.S. markets studied.
What is happening in San Antonio and Austin?
JLL combines Austin and San Antonio into one market. Its midyear 2026 release says the corridor completed 1.7 GW and absorbed 796 MW in the first half, as development moved out from the urban cores along I-35. In H1 2024, by contrast, CBRE counted only 189.7 MW of Austin/San Antonio inventory, 463.5 MW under construction, 1.8% vacancy and 26.9 MW of net absorption for the half.
Propmodo reported Cushman & Wakefield data for the corridor in March 2026: 1,154 MW operating, 615 MW under construction and 96% preleased, and 7,823 MW planned across more than 70 projects from Temple to San Antonio. The same article cited Colliers’ 2026 Data Center Marketplace report, which measured the Austin market alone at 645 MW, with 120 MW of annual absorption and 0.6% vacancy.
DC Byte wrote in March 2026 that San Antonio’s take-up is 2.4 times its live supply, meaning mega-campus commitments are piling up faster than construction can start.
Is there enough data to size Houston?
Not from the H1 2026 headline releases, which do not break Houston out. Construction filings are the clearest signal, such as a $300 million, 189,060-square-foot building registered as “Project Eagle – Building D” by Amazon Data Services in Boling, Wharton County, southwest of Houston, with work scheduled from August 2026 to January 2027.
Which colocation campuses are under construction in Texas right now?
Registrations with the Texas Department of Licensing and Regulation (TDLR) and company announcements identify buildings behind the broker totals. TDLR records list costs and dates, not megawatts.
| Project | Location | Scale / cost | Schedule |
|---|---|---|---|
| Stream Data Centers DFWC1 | Wilmer, Dallas County | $300M; 360,750 sq ft | Apr 2026 – Oct 2027 |
| ACS Hicks Field DFW11 | North Fort Worth, Tarrant County | $280M; 251,303 sq ft | Jan 2026 – Jun 2027 |
| ACS DFW13 Hicks Field | North Fort Worth, Tarrant County | $100M; 283,274 sq ft | Jan 2026 – Jan 2028 |
| ACS DFW12 Hicks Field | North Fort Worth, Tarrant County | $100M; 283,274 sq ft | Aug 2026 – May 2028 |
| Vantage Data Centers TX12 | West San Antonio, Bexar County | $276.9M; 432,800 sq ft | Oct 2025 – Aug 2027 |
| Rowan Digital Infrastructure “Cinco” | Near Lytle, Medina County | 300 MW; 440 acres; $900M+ | Broke ground Aug 2025; operations expected 2027 |
| CyrusOne SAT14 (Castroville) | Medina County, west of San Antonio | About 244 acres | Construction began 2026; first building 2027 |
Source: Texas Department of Licensing and Regulation TABS project registrations (Stream DFWC1, Hicks Field DFW11/DFW12/DFW13, Vantage TX12); Government Technology and Data Center Map (Rowan); Baxtel (CyrusOne SAT14). Data accessed November 2026.
What is being built in North Fort Worth?
The Hicks Field buildings belong to a 107-acre campus in north Fort Worth planned by ACS, the Madrid-based construction and infrastructure group. A 10-year Fort Worth incentive agreement approved in April 2025 requires at least $2 billion of investment across five buildings, with Phase 1 due by the end of 2031. With three buildings registered for 2026–2028, construction is running well ahead of that deadline.
Which large Texas campuses are paired with power plants?
CyrusOne is building two campuses south of the metroplex next to existing gas-fired plants. In Bosque County, the first building of a campus targeting more than 400 MW and paired with Calpine’s Thad Hill Energy Center topped out in March 2026. That building, DFW10, was reported at about $750 million and 250,000 square feet. In Freestone County, about 90 miles south of Dallas, CyrusOne broke ground in early June 2026 on a campus next to Calpine’s 1 GW Freestone Energy Center, backed by two 380 MW agreements with Constellation.
What is planned but not yet under construction?
Flexential announced in July 2026 its fourth and largest DFW campus: 110 acres in Talty, Kaufman County, planned for three 36 MW buildings (108 MW in total). Power for the 36 MW first phase is secured. Site work starts in early 2027, with first customer availability in late 2028.
What do the numbers mean for Texas companies buying or building capacity?
Three conclusions follow. DFW has the most open colocation capacity of any primary market, but 39.6 MW is less than one large AI deployment, and 95% of space under construction is already leased, so tenants needing megawatts in 2027 are competing for buildings not yet finished. The Austin-San Antonio corridor has gone from niche to gigawatt scale in two years. And rents are rising in every size band, so expiring contracts will likely renew higher.
The year-end 2026 broker reports will show whether these pipelines delivered on schedule.
Frequently Asked Questions
What is the Dallas-Fort Worth data center inventory in 2026?
CBRE counts 1,432.8 MW of colocation inventory as of H1 2026; JLL’s broader count is 4,587 MW.
What is the DFW data center vacancy rate?
CBRE reports 39.6 MW available against 1,432.8 MW of inventory, about 2.8%, as of H1 2026. JLL puts DFW vacancy below 1%. The primary-market average in CBRE’s report is 1.4%.
How much capacity is under construction in Dallas-Fort Worth?
More than 765 MW by CBRE’s H1 2026 count, 95% preleased, plus 3.7 GW of planned greenfield projects. JLL’s wider count is 3,202 MW.
How much data center capacity did Austin and San Antonio add in 2026?
JLL says the combined Austin/San Antonio market completed 1.7 GW and absorbed 796 MW in the first half of 2026.
Are data center rents still rising?
Yes. CBRE’s H1 2026 report shows asking rates up 4.3% to 8.3% year over year depending on deployment size, after the 2025 North American average reached $194.95 per kW per month. JLL says rents are up nearly 70% since 2020.
Sources and Further Reading
- North America Data Center Trends H1 2026 (report and Dallas-Ft. Worth chapter) — CBRE
- North American Data Center Demand Continues to Outpace Supply Despite Record Construction Activity, August 27, 2026 — CBRE
- Fast-Growing North American Data Center Market Set Records in 2025, February 26, 2026 — CBRE
- North America Data Center Trends H1 2025: Dallas-Ft. Worth Market Profile — CBRE
- Data Center Construction Quadruples in Central Texas (Austin/San Antonio H1 2024), August 21, 2024 — CBRE
- Data Center Demand Exceeds Expectations as H1 2026 Absorption Hits Record 25 GW, August 11, 2026 — JLL
- Americas Data Center Update H1 2026 — Cushman & Wakefield
- Dallas, Texas Ranked No. 1 Primary Data Market in the World (2026 Global Data Center Market Comparison) — Cushman & Wakefield via Business Wire
- Dallas-Fort Worth Dethrones Virginia as the World’s Top Data Center Market, August 18, 2026 — Dallas Innovates
- DFW Data Center Demand Remains Hot as Pre-Leasing Hits 95%, September 3, 2026 — Dallas Innovates
- Central Texas’s Data Center Boom Is Repricing Land, Power, and Industrial Development, March 31, 2026 — Propmodo
- Five Structural Shifts Defining the Texas Data Center Market — DC Byte
- TABS project registrations — Texas Department of Licensing and Regulation
- $2B Data Center Project Moves Forward in Fort Worth, April 2025 — CommercialSearch
- Flexential Plans Largest Dallas-Area Data Center Campus, July 28, 2026 — Flexential
- CyrusOne Breaks Ground on 380MW Campus Co-Located With Texas Natural Gas Plant, June 2026 — IDC Nova
- CyrusOne Tops Out Latest Texas Data Center, March 2026 — Pulse
- Denver Company Building $900M Data Center West of San Antonio, August 2025 — Government Technology
- CyrusOne Castroville SAT14 Campus profile — Baxtel