ERCOT's data center audit drew responses from 433 of 465 loads covering 177 GW. See what Texas is verifying, what is paused and the December 10 report timeline.

Quick Answer: ERCOT’s data center audit, ordered by Gov. Greg Abbott on August 3, 2026, sent information requests to 465 large and medium loads, and 433 responded, covering about 97% of roughly 177 GW of requested capacity, according to ERCOT’s November 5 update. All 245 large loads of 75 MW or more responded. ERCOT targets a final report on December 10, with Public Utility Commission review on December 17.

Texas’ data center boom hit a regulatory checkpoint this year. In early August, Governor Greg Abbott directed the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) to verify and audit every data center moving through the state’s grid interconnection process before any project advances. Three months later, ERCOT has collected responses from hundreds of developers, and the results are due in December.

This report explains what the directive requires, what ERCOT has done so far, the numbers in its November 5 update and the timeline ahead. It draws on the governor’s directive, ERCOT’s presentations to the PUCT, an ERCOT market notice, and coverage and legal analysis from the Texas Tribune, Utility Dive, DatacenterDynamics, Gibson Dunn, Holland & Knight and Greenberg Traurig.

What did Governor Abbott order?

On August 3, 2026, Abbott directed the PUCT and ERCOT to conduct “a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process.” His release said the two agencies “must complete this audit before any data center project moves forward,” and that projects that fail must be denied connection to the grid. The directive built on an earlier June 10 directive.

The governor’s office said ERCOT was considering more than 474 gigawatts of interconnection requests, more than five times the grid’s record peak demand, and that about 90% of new requests came from data centers. The Texas Tribune, citing ERCOT, reported more than 1,800 projects in the queue.

What does the audit cover?

The directive lists five areas:

  • Financial incentives: tax incentives, grants, abatements and other public assistance.
  • Power sourcing: projected annual and peak consumption and any on-site generation.
  • Water use: projected annual and peak consumption, water sources and cooling technology.
  • Community impact mitigation: noise, light, setbacks, traffic and emergency response.
  • Ownership: ownership and controlling interests.

Is it a moratorium?

Descriptions differ. The Texas Tribune’s headline said data center approvals were halted until audits were completed, and Utility Dive described the directive as a call for a moratorium. Law firm Gibson Dunn, in an August 14 analysis, wrote that the directive is “not a moratorium on data center development.” In practice, ERCOT paused certain steps for large data centers while it verifies them, as described below.

What did ERCOT pause?

ERCOT told the PUCT on August 20 that on August 3 it issued a market notice pausing its Batch Zero study, delaying final classification of projects, and pausing energization approvals for data center and cryptocurrency facilities of 75 MW or more. Batch Zero is ERCOT’s process for studying large loads of 75 MW and above as a group. On August 10, ERCOT filed three good-cause exception requests related to the process.

ERCOT asked to conditionally classify Batch Zero loads by August 31 instead of August 7. It said 17 large loads, totaling 6,608 MW of peak demand over five years, had completed every ERCOT process except energization approval and were waiting under the pause. ERCOT also reported reviewing 290 dynamic models from large-load developers, with about 18% acceptable on first review.

ERCOT Large-Load Status Figures (Aug. 20, 2026 PUCT Presentation)
Large loads awaiting only energization approval 17 loads; 6,608 MW peak over five years
Loads expected in Aug. 1 stability assessment 6 loads; about 1,959 MW
Loads potentially eligible for Nov. 1 assessment 17 loads; about 6,874 MW
Dynamic models reviewed 290; about 18% acceptable on first review
Medium data center and crypto loads (April snapshot) 157 loads; about 8,766 MW
Batch Zero study-results deadline April 9, 2027

Source: ERCOT, Batch Zero Verification and Audit presentation to the PUCT.

How did ERCOT collect the data?

On September 14, 2026, ERCOT issued a State and Community Impact request for information to developers of data centers of 25 MW or more. The notice covered Batch Zero large loads conditionally classified as base or studied load that had not energized at 60 kV or above, plus medium-load developers of 25 MW to under 75 MW identified in an August 19 survey. Transmission and distribution providers had two business days to submit developer contacts.

Responses, including a notarized attestation, were due at 5 p.m. Central on October 12, 2026. ERCOT said non-responses would be reported to the PUCT and the Governor’s Office. Water questions were included for the Texas Water Development Board, and ERCOT warned that failure to respond to them could carry criminal penalties under the Texas Water Code.

What did ERCOT’s November 5 update show?

ERCOT’s preliminary update to the PUCT on November 5 reported that the RFI went to 465 loads and that 433, or 93%, submitted responses. Those respondents represent about 97% of the roughly 177 GW of capacity requested, including about 166 GW from large loads. All 245 large loads of 75 MW or more responded. Of the submissions, 417 arrived on time and 16 were late, while 32 medium-load responses were not submitted.

ERCOT Community Impact RFI Results (Preliminary, Nov. 5, 2026)
Loads receiving RFI 465
Responses submitted 433 (93%)
On time / late 417 / 16
Medium-load responses not submitted 32
Large loads (75 MW+) responding All 245
Total capacity requested About 177 GW
Large-load capacity About 166 GW (about 94%)
Share of capacity responding About 97%
Questions answered 83% of nearly 67,000 (about 56,000 data points)
Projects over 1 GW 33 (36% of capacity)
Largest zone West Texas, 41% (73 GW)
Final report target December 10, 2026

Source: ERCOT Community Impact RFI PUC Update, marked preliminary and subject to change.

What do the numbers reveal about project size and location?

Thirty-three projects each request more than 1 GW and together account for 36% of the requested capacity, or roughly 64 GW. West Texas is the largest zone, with 41% of capacity, about 73 GW. Respondents answered 83% of nearly 67,000 questions, and cooling was the category with the largest share of “not applicable” answers.

The update also addressed cryptocurrency mining. About 95% of facilities, representing more than 99% of capacity, or 175.9 GW, reported no virtual currency mining. Twenty-two facilities reported some mining, 20 of them medium loads.

How does this compare with the earlier voluntary survey?

The response rate is a sharp change from earlier this year. The Texas Tribune reported in August that when PUCT staff notified 377 companies about a prior data center survey, only 28 submitted responses, a participation level one legislator called “pretty pathetic.” The mandatory RFI, backed by attestation requirements and reporting to state leaders, produced responses from 93% of recipients and every large load.

Data Center Audit Timeline
Date Event
June 10, 2026 Earlier gubernatorial directive on data centers
Aug. 3, 2026 Abbott directs audit; ERCOT pauses Batch Zero study and large-load energization approvals
Aug. 10, 2026 ERCOT files good-cause exception requests
Aug. 14 and 20, 2026 PUCT open meetings on the audit
Aug. 19, 2026 House State Affairs Committee hearing
Sept. 14, 2026 ERCOT issues State and Community Impact RFI
Oct. 12, 2026 RFI responses due
Nov. 5, 2026 ERCOT preliminary update to PUCT
Dec. 10, 2026 Verification and community impact reports due
Dec. 17, 2026 PUCT open meeting on results
April 9, 2027 Batch Zero study-results deadline (ERCOT says it will not be met)

How many data centers does Texas have?

The Texas Tribune counted at least 335 data centers operating in Texas and at least 248 more planned as of August 2026. The audit population is broader than that count because it includes projects at every stage of interconnection, from early requests to facilities awaiting final energization approval, and it includes cryptocurrency mining operations of 25 MW and above alongside conventional data centers.

The medium-load group is also significant. ERCOT’s April snapshot counted 157 medium data center and crypto loads totaling about 8,766 MW, close to the 9,456 MW of large loads ERCOT had approved to energize by October. Medium loads of 25 MW to under 75 MW fall outside Batch Zero but were included in the community impact review.

How has the industry responded?

Industry reaction has been mixed but largely cooperative. The Data Center Coalition told the Texas Tribune that the review could showcase the good actors in the industry. Holland & Knight reported that a senior House committee member said he intends to pursue legislation repealing the sales tax exemption for data centers, a sign that the audit’s findings on incentives could have direct financial consequences for the sector.

What happens next?

ERCOT plans to file its Batch Zero eligibility verification report and community impact review report on December 10, with a PUCT open meeting on December 17. Utility Dive reported that ERCOT intends to audit about 300 data centers of 75 MW or more in Batch Zero, and quoted Seely of ERCOT as saying, “We will not have the study done by April 9, 2027.” ERCOT was still working on a new timeline.

Gibson Dunn noted that ERCOT’s long-term load forecast, which had been expected by mid-August, was delayed by the process. Holland & Knight reported that at the August 19 House State Affairs hearing, regulators acknowledged they lack explicit authority over the community-impact items and would rely on voluntary attestations, and that the PUCT chairman said the audit results will shape legislation in the 90th session.

What does this mean for developers and investors?

The audit has turned verification into a gating step before interconnection studies rather than a parallel task, Holland & Knight noted. For developers, that means schedule risk: the 17 large loads waiting only on energization approval, totaling about 6.6 GW, show how much capacity is held up by the pause. For communities and local governments, the audit’s questions on tax incentives, water and nuisance impacts will produce the most comprehensive dataset yet on how Texas data centers affect the places they are built.

For the grid, the stakes are large. ERCOT’s October operational overview showed 9,456 MW of large loads already approved to energize, a fraction of the roughly 177 GW covered by the RFI. How many of the audited projects are confirmed, and how quickly, will shape ERCOT’s planning and Texas’ power supply decisions in 2027.

Frequently Asked Questions

Why is Texas auditing data centers?

Governor Abbott directed the PUCT and ERCOT on August 3, 2026, to verify data centers in the interconnection queue, citing more than 474 GW of requests, about 90% from data centers.

How many data centers responded to ERCOT’s audit?

ERCOT reported that 433 of 465 loads responded, including all 245 large loads of 75 MW or more, covering about 97% of roughly 177 GW of requested capacity.

When will the data center audit be finished?

ERCOT plans to file its reports on December 10, 2026, with a PUCT open meeting on December 17.

Did Texas impose a data center moratorium?

Some outlets described the directive as a moratorium, while Gibson Dunn said it is not one. ERCOT did pause its Batch Zero study and energization approvals for 75 MW-plus data center and crypto loads pending verification.

What is Batch Zero?

Batch Zero is ERCOT’s grouped study process for large loads of 75 MW and above, with a study-results deadline of April 9, 2027, that ERCOT has said it will not meet.

Sources and Further Reading

  1. Governor Abbott Directs Comprehensive Data Center Audit, Office of the Texas Governor
  2. Community Impact RFI PUC Update, November 5, 2026, Electric Reliability Council of Texas
  3. Batch Zero Verification and Audit PUCT Presentation, August 20, 2026, Electric Reliability Council of Texas
  4. Market Notice M-B091426-01, State and Community Impact RFI, Electric Reliability Council of Texas
  5. Data Center Approvals in Texas Halted Until Audits Completed, Gov. Greg Abbott Says, The Texas Tribune
  6. ERCOT, Texas PUC Data Center Audit, Utility Dive
  7. ERCOT to Complete Texas Data Center Audit by December, DatacenterDynamics
  8. What Governor Abbott’s Data Center Audit Directive Means for ERCOT and the Batch Zero Study Process, Gibson Dunn
  9. Data Center Industry Responds in Wake of Texas Regulatory Changes, Holland & Knight
  10. Texas Imposes New Audit Requirement for Data Center Projects, Greenberg Traurig
  11. ERCOT Monthly Operational Overview, October 2026, Electric Reliability Council of Texas