Quick Answer: Vantage Data Centers’ Frontier campus in Shackelford County is a planned 1.4 GW, 10-building, 3.7-million-square-foot data center development on about 1,200 acres, with an investment of more than $25 billion. Vantage scheduled the first building for delivery in the second half of 2026 and full completion in 2028, and trade reports tie the campus to Oracle and OpenAI’s Stargate initiative.
Shackelford County, northeast of Abilene, is home to about 3,200 people. It is also the site of one of the largest single data center investments ever announced in Texas. Vantage Data Centers’ Frontier campus, unveiled in August 2025, carries a price tag of more than $25 billion and a planned capacity of 1.4 gigawatts, placing it among the biggest AI computing projects in the country.
This report compiles the public details on Frontier from Vantage’s announcement, trade coverage of its groundbreaking and power arrangements, Industrial Info Resources’ tracking of Texas data center construction, and Census Bureau data on the county where it is being built. It also places the project in the context of the statewide data center pipeline and the policy questions now facing it.
What is the Vantage Frontier data center campus?
Vantage Data Centers announced Frontier on August 19, 2025, describing it as its largest investment to date. The campus covers about 1,200 acres in Shackelford County and is planned to include 10 data centers totaling 3.7 million square feet, with 1.4 GW of capacity designed for GPU computing. Vantage said the buildings would support ultra-high-density racks of 250 kilowatts or more using liquid cooling.
W.Media reported in December 2025 that the 10 facilities will be single-story buildings with a combined capacity of 1.4 GW, each with three meet-me rooms for network interconnection, and that the campus uses both air and liquid cooling. It described the site as about 125 miles west of Fort Worth near Abilene.
| Developer | Vantage Data Centers |
| Location | Shackelford County, Texas (near Abilene) |
| Site size | About 1,200 acres |
| Buildings | 10 single-story data centers |
| Floor area | 3.7 million square feet |
| Capacity | 1.4 GW |
| Investment | More than $25 billion |
| Rack density | 250 kW+ per rack, liquid cooling |
| Jobs | More than 5,000 across construction and operations |
| First building | Scheduled for second half of 2026 |
| Full completion | Scheduled for 2028 |
| Reported tenant link | Oracle and OpenAI Stargate initiative (W.Media) |
Sources: Vantage Data Centers via Business Wire; W.Media; MarketScale.
Who will use the Frontier campus?
Vantage did not name a tenant in its August 2025 announcement. W.Media reported that the campus is tied to Oracle and OpenAI’s Stargate initiative and is part of the two companies’ previously announced partnership to invest in up to 4.5 GW of additional Stargate capacity, noting that Oracle and OpenAI were officially linked to the project in October 2025.
Industrial Info Resources, in an August 2026 report on Texas data center construction, described a second Stargate campus in Shackelford County, about 40 miles northeast of Abilene, with 10 buildings, in addition to the flagship Stargate campus in Abilene’s Taylor County. Stargate, announced January 21, 2025, is a venture of OpenAI, Oracle, SoftBank and MGX that originally planned up to $500 billion of investment by 2029.
How does Frontier compare with other Texas mega-campuses?
Industrial Info tracked about $89.5 billion of data center construction under way in Texas as of August 2026, across about 30 counties. Taylor County, home to the Abilene Stargate campus, led the state in spending, with 10 buildings under construction there. Google’s campus in Gray County near Pampa, served by the Southwest Power Pool rather than ERCOT, includes four buildings of about 750,000 square feet each, each requiring 210 MW, with an estimated total investment of $14 billion.
| Project | County | Buildings | Power / Capacity | Investment |
|---|---|---|---|---|
| Vantage Frontier | Shackelford | 10 | 1.4 GW | More than $25B |
| Stargate Abilene | Taylor | 10 under construction | 1,015 MW gas plant near completion | Leads Texas spending (IIR) |
| Google (Pampa area) | Gray | 4 (about 750,000 sq. ft. each) | 210 MW per building; SPP grid | About $14B |
Sources: Vantage Data Centers; Industrial Info Resources.
Where else is construction under way?
Industrial Info’s August 2026 survey listed a broad spread of projects beyond West Central Texas. In addition to the Abilene and Shackelford County campuses, it identified a Stargate campus in Milam County in Central Texas. Google, beyond its Gray County site, has campuses in Wilbarger, Haskell and Ellis counties, including two in Ellis County, and expects the fourth Gray County building in the second half of 2027. With about 30 Texas counties hosting active data center construction, the industry is no longer concentrated in Dallas-Fort Worth and San Antonio.
What is the Frontier timeline?
| Date | Milestone |
|---|---|
| Jan. 21, 2025 | Stargate venture announced by OpenAI, Oracle, SoftBank and MGX |
| Aug. 19, 2025 | Vantage unveils Frontier; says construction has begun |
| Oct. 2025 | Oracle and OpenAI officially linked to the project (W.Media) |
| Dec. 2025 | Vantage announces groundbreaking |
| Aug. 2026 | Industrial Info tallies $89.5B of Texas data center construction; governor orders moratorium on new approvals |
| Second half of 2026 | First Frontier building scheduled for delivery |
| 2028 | Full campus completion scheduled |
Sources: Vantage Data Centers, W.Media, Industrial Info Resources.
What do the per-unit numbers show?
Dividing Vantage’s announced figures gives a sense of the project’s intensity. At more than $25 billion for 1.4 GW, Frontier represents roughly $17.9 million of investment per megawatt of capacity. Its 1.4 GW spread across 3.7 million square feet works out to about 378 watts per square foot, and the average building would hold about 140 MW and 370,000 square feet. Those calculations are based on announced totals and will shift as buildings are fitted out.
How will the Frontier campus be powered?
Power is the defining constraint for projects of this size. Industrial Info reported that a 700 MW gas-fired plant was in planning to support the Shackelford County Stargate campus, while a 1,015 MW simple-cycle plant was nearly complete to support the Abilene campus’s first 10 buildings. Industrial Info said the gas generation projects for the two campuses total more than $1 billion.
MarketScale, writing in September 2026, argued that the grid interconnection and power-delivery agreements, rather than construction, are the real schedule drivers for Frontier, though it did not disclose a specific utility, substation or amount of grid service. Industrial Info noted that ERCOT carries about 90% of the state’s power load and that applications for new interconnections have exceeded the grid operator’s peak capacity several times over.
Is ERCOT able to supply campuses this large?
ERCOT’s own figures show the scale of the challenge. In its October 2026 operational overview, ERCOT reported that 9,456 MW of large loads had received approval to energize, with observed peak consumption from those loads of 5,115 MW in October. Frontier alone, at 1.4 GW, would equal roughly 15% of that approved large-load total. Pairing a campus with dedicated on-site or nearby gas generation is one way developers are trying to bring capacity online without waiting on transmission upgrades.
The supply side of the grid is responding. ERCOT reported 1,847 active generation interconnection requests totaling 461,414 MW as of October 31, 2026, including 95,032 MW of natural gas requests, nearly double the 47,848 MW a year earlier. Requests are not commitments to build, but the jump in gas filings shows developers positioning dispatchable plants for exactly the kind of large, around-the-clock demand that campuses like Frontier create. Not every Texas campus depends on ERCOT, however: Industrial Info noted that Google’s Gray County site in the Panhandle is served by the Southwest Power Pool, a reminder that location within the state determines which grid, and which set of rules, a project must navigate.
What does Frontier use for cooling and water?
Vantage said Frontier will use a closed-loop chiller system that requires minimal water for cooling, and that the company is pursuing LEED certification. Closed-loop systems recirculate coolant rather than evaporating water, which matters in a semi-arid part of West Central Texas. The use of liquid cooling for racks of 250 kW or more is consistent with the high heat loads of AI GPU clusters.
What does a $25 billion campus mean for Shackelford County?
The contrast between the project and its host county is stark. Census Bureau estimates put Shackelford County’s population at 3,197 on July 1, 2025, with 1,591 housing units and a land area of about 914 square miles. The 1,200-acre Frontier site, about 1.9 square miles, covers roughly 0.2% of the county’s land, so the project’s physical footprint is small even though its economic footprint is enormous. Census County Business Patterns data counted total employment of 1,066 in the county in 2023, and the median household income for 2020 to 2024 was $73,047.
Vantage said Frontier would employ more than 5,000 people across construction and ongoing operations. Many of those workers are likely to come from outside the county, since that figure is nearly five times the county’s 2023 employment. Neighboring Taylor County, home to Abilene, had 150,077 residents and 61,016 jobs, and will likely supply much of the housing, services and workforce.
| Measure | Shackelford County | Taylor County |
|---|---|---|
| Population, July 1, 2025 | 3,197 | 150,077 |
| Housing units, July 1, 2025 | 1,591 | 63,895 |
| Total employment, 2023 | 1,066 | 61,016 |
| Median household income (2020-24) | $73,047 | $67,139 |
| Land area (sq. mi.) | 914.29 | 915.54 |
Source: U.S. Census Bureau QuickFacts.
At more than $25 billion, Frontier’s announced investment works out to roughly $7.8 million per Shackelford County resident. Even if much of the value is in computing equipment rather than taxable real property, a project of this size can reshape a small county’s tax base, road needs and public services.
What policy risks face Texas data center projects?
Industrial Info reported that, in the same week as its August 2026 report, Governor Greg Abbott issued a moratorium on new data center approvals until a comprehensive verification and audit is completed. The review, directed at the Public Utility Commission and ERCOT, covers power and water use, community impacts such as noise and light, ownership verification and the tax breaks projects receive. Projects already under construction, like Frontier, face a changing policy environment even as they move toward completion.
Brian’s Take
Start with the ratio that jumps off the page: about $7.8 million of announced investment for every resident of Shackelford County, and a promised workforce nearly five times the county’s total 2023 employment. That is not a local economic development story in the usual sense. It is a regional one, and Abilene and Taylor County will carry much of the load on housing, services and roads.
The second point is power. A 1.4 GW campus is about 15% of all the large load ERCOT had approved to energize as of October. Industrial Info’s report of a 700 MW gas plant planned for the Shackelford campus tells you developers are not counting on the grid alone. That is the right instinct, but it means the schedule depends on turbines, pipelines and permits as much as on buildings.
Finally, the moratorium matters. Frontier was announced, broke ground and has its first building scheduled in a friendlier policy climate than the one it will finish in. I would watch the outcome of the state’s audit closely, because it will shape how the next generation of these projects is approved, taxed and powered.
Frequently Asked Questions
Where is the Vantage Frontier data center?
Frontier is in Shackelford County, Texas, on about 1,200 acres near Abilene and roughly 125 miles west of Fort Worth.
How much is Vantage investing in Frontier?
Vantage announced an investment of more than $25 billion, its largest to date.
How much power will Frontier use?
The campus is planned for 1.4 GW of capacity across 10 buildings, with racks of 250 kW or more.
When will the Frontier campus open?
Vantage scheduled its first building for delivery in the second half of 2026, with full completion scheduled for 2028.
Is Frontier part of Stargate?
W.Media reported that the campus is tied to Oracle and OpenAI’s Stargate initiative. Vantage’s own announcement did not name a tenant.
Sources and Further Reading
- Vantage Data Centers Unveils Plans for “Frontier,” a $25B Mega-Campus in Texas to Meet Unprecedented AI Demand, Vantage Data Centers (Business Wire)
- Vantage Data Centers Breaks Ground on Data Center Campus in Texas, W.Media
- Vantage’s 1.4GW Texas Campus Makes Grid Contracts the Real Data Center Schedule, MarketScale
- Abilene’s Stargate Project Campus Leads Texas’ $89.5 Billion in Active Data Center Construction, Industrial Info Resources
- QuickFacts: Shackelford County and Taylor County, Texas, U.S. Census Bureau
- ERCOT Monthly Operational Overview, October 2026, Electric Reliability Council of Texas