Texas cities and counties gave data centers $1B+ in local tax breaks via Chapter 312 and 380/381 deals. See which 2026 deals passed or failed, and JETI's role.

Quick Answer: Texas cities and counties, not the state, decide most property tax breaks for data centers. They use 10-year Chapter 312 abatements and open-ended Chapter 380/381 agreements. A November 2026 Texas Tribune analysis found 53 local agreements covering 34 data centers and at least $1 billion in forgone local taxes. School districts cannot grant abatements, and the state’s JETI program was not built with data centers in mind.

The state sales tax exemption gets most of the attention, but city councils and commissioners courts decide how much Texas data centers pay in property taxes. In 2026 those bodies approved some multibillion-dollar deals and rejected others.

How do local property tax incentives for data centers work in Texas?

Texas has three main local tools, and they operate differently from the state sales tax exemption. The sales tax break covers equipment purchases and is set in state law. Local incentives cover property taxes on land improvements and business personal property such as servers and electrical gear, and each one is negotiated by the city or county that levies the tax.

What is a Chapter 312 tax abatement?

Under Chapter 312 of the Tax Code, cities, counties and special districts may exempt all or part of the increase in a property’s value from taxation, according to the Texas Comptroller. Agreements may last no longer than 10 years, and the value of the property on January 1 of the year the agreement is signed stays taxable. The property must sit in a reinvestment zone, which the city or county designates after adopting guidelines and holding a public hearing with seven days’ notice. A zone designation lasts five years and can be renewed.

Agreements must require annual compliance certification and allow recapture of lost revenue. The Comptroller also states directly that “school districts may not enter into abatement agreements.”

How are Chapter 380 and 381 agreements different?

Chapter 380 of the Local Government Code covers cities and Chapter 381 covers counties. These agreements let local governments give grants, loans or infrastructure help, often structured as rebates that offset property taxes. The Texas Tribune reported in November 2026 that these are the most common tools used for data centers and that, unlike Chapter 312 abatements, they do not have to expire. Of the data center agreements the Tribune identified, at least 32 were active under Chapters 380 or 381, plus one terminated, and about 12 more were under Chapter 312.

Tool Who grants it What it covers Maximum term
Chapter 312 abatement Cities, counties, special districts (not school districts) Exempts part or all of new property value 10 years
Chapter 380 / 381 agreement Cities (380), counties (381) Grants, loans, rebates, infrastructure No required expiration
JETI (Chapter 403) School district with governor’s approval 50% limit on value for school M&O tax 10-year incentive period
State sales tax exemption State, through the Comptroller Sales and use tax on qualifying equipment Set by state law

How much have Texas local governments given data centers?

The most complete count comes from a Texas Tribune analysis published November 17, 2026. Reporters matched the Comptroller’s database of local economic development agreements against nearly 600 operating and planned data centers. They found 53 local tax agreements covering 34 data centers and at least $1 billion in local property tax breaks. The agreements guaranteed 465 jobs in total, and roughly half had no job requirement at all. At least 25 Texas data centers receive both state and local breaks.

The Tribune said the totals are likely an undercount. Data centers often negotiate through shell companies, and many governments did not report the financial details the state requires. One deal, Meta’s El Paso agreement, accounts for more than half of the $1 billion.

Which local data center deals carry the largest dollar values?

Jurisdiction Company Terms Value / status
Fort Worth Meta 20-year rebates; 40 jobs required At least $271 million
Red Oak Google Up to 85% abated through 2031; 40 jobs; $300M investment About $2.8 million abated to date
Ellis County Compass At least 75% property tax rebate Active
San Antonio Microsoft (2013) 20 jobs required $5.4 million in rebates received
Dallas County Equinix (2021) 10 years; 25 jobs required About $910,000 abated
Guadalupe County CloudBurst Abatement plus 10-year development agreement About $500 million; approved April 2026
Brazos County / Bryan RELLIS data center 40 years; taxes on 50% of value for first 10 years Approved 2026 for new owner
Brazoria County Nightpeak Energy Four 10-year, 100% abatements requested Denied unanimously, March 2026
Cameron County SpaceX 100% for 10 years requested Talks rejected 3-2, November 2026

What did Guadalupe County approve for CloudBurst?

The CloudBurst case shows how quickly a local vote can change. In February 2026, Guadalupe County commissioners voted 3-2 against a Chapter 312 abatement worth about $500 million for CloudBurst Texas, Community Impact reported. The project covers about 220 acres on Francis Harris Lane in New Braunfels, split between Guadalupe and Hays counties, and calls for 12 AI buildings totaling 3 million square feet.

On April 21, the commissioners court approved a revised package, The Real Deal reported. It included the estimated $500 million abatement and a 10-year development agreement that lets the developer proceed under current county rules even if regulations change. County records put total investment at $14.5 billion, with 480 jobs expected over six years, projected water use of 24,000 gallons per day, and the first four buildings targeted for 2027. CloudBurst has told the county it plans to generate power behind the meter.

Why are some counties rejecting data center abatements?

Several 2026 votes went the other way, and county officials often acknowledged that rejecting an abatement does not stop a project.

What happened in Brazoria County?

In March 2026, Brazoria County commissioners unanimously denied four 10-year, 100% abatements requested by Nightpeak Energy for its $3.5 billion Old Ocean Data Center near Sweeny, Bisnow reported. The project calls for two 310 MW data centers and two 310 MW combustion turbine plants on 158 acres, with about 30 permanent jobs. County Judge Matt Sebesta said the project would likely go forward anyway.

What happened with SpaceX in Cameron County?

In November 2026, Cameron County commissioners voted 3-2 against moving ahead with abatement talks for a proposed $24 billion SpaceX data center and natural gas power plant on a 444-acre site in the county’s enterprise zone near Starbase, Newsweek reported. SpaceX had asked for a 100% abatement for 10 years. The article did not report the reasons commissioners gave for voting no.

Why did Fort Worth’s Edged deal fall apart?

In Fort Worth, Edged U.S. sought a 10-year abatement on 50% of business personal property taxes, an estimated $18.2 million, for a $1.1 billion, two-building campus on 186 acres, The Real Deal reported. The deal required at least 50 jobs paying at least $73,000. After the council tabled the vote on March 31 over resident objections, Edged withdrew its application before a scheduled May 12 vote, KERA reported.

Can counties use abatements to set conditions on water and power?

Texas counties have little zoning authority, and Floyd County is using that fact to argue for an abatement rather than against one. RFD-TV reported in August 2026 that Floyd County commissioners were considering a Chapter 312 agreement for a proposed Amazon campus valued at more than $1 billion, with seven buildings on about 485 acres. The terms under discussion would require air-cooled systems to reduce groundwater demand and on-site power generation so the facility does not compete with homes, farms and businesses during shortages. Officials said that without an agreement, private property protections and limited zoning power would leave them with little influence. The article did not give the abatement’s percentage, length or value.

The RELLIS project in Bryan shows the same kind of control at the city level. The Bryan City Council approved a replacement abatement in June 2026 after the original developer filed for Chapter 11 in November 2025, KBTX reported. The project requires at least $298 million in improvements on a 25-acre Texas A&M System tract. In August, Brazos County commissioners voted 4-0 to approve a 40-year agreement with new owner ThisWay Global for what the county described as a $700 million project. The county will collect taxes on 50% of taxable value for the first 10 years and 100% for the remaining 30 years. Because the A&M System owns the land, the property would otherwise be off the tax rolls.

Do school districts give data centers tax breaks?

School district property taxes are usually the largest part of a Texas tax bill, but districts cannot grant Chapter 312 abatements. Their main incentive tool for large projects was the Chapter 313 value limitation program, which no longer accepts applications. Existing agreements remain in effect until they expire.

Can data centers use the JETI program under Chapter 403?

JETI, created by House Bill 5 in 2023, replaced Chapter 313. It limits the taxable value of a project for school district maintenance and operations (M&O) taxes to 50% of market value, or 25% in a qualified opportunity zone, for 10 years. Value is limited to zero during construction. It does not reduce interest and sinking taxes that pay school debt. A project needs approval from both the school district and the governor’s office, must pay a $30,000 application fee, and is barred from making the payments in lieu of taxes that were common under Chapter 313.

The governor’s office lists eligible categories as manufacturing, dispatchable electric generation, natural resource development, high-tech research and manufacturing, and critical infrastructure. Data centers are not named. The statute names only two exclusions, nondispatchable generation and energy storage. The Comptroller’s JETI FAQ does not address data centers. KBTX, covering the Terafab semiconductor project’s JETI filings with Iola ISD and Anderson-Shiro CISD in June 2026, reported that JETI excludes data centers. Because dispatchable generation is eligible, a gas plant built to serve a data center could in principle qualify even if the data center itself does not.

JETI minimums by county population Jobs Investment
750,000 or more 75 $200 million
250,000 to 749,999 50 $100 million
100,000 to 249,999 35 $50 million
99,999 or less 10 $20 million

How do local incentives differ from the state sales tax exemption?

The differences are about who decides, how long the deal lasts, and what is required in return. The state exemption applies to qualifying equipment purchases under rules set in state law. Local incentives are negotiated one at a time, and the terms vary widely, from a 10-year Chapter 312 abatement to a 40-year arrangement like Brazos County’s. The Comptroller’s July 2026 audit found that one in five of 20 audited data centers fell short of the state program’s 20-to-40 job requirement, the Tribune reported. Local agreements often require fewer jobs or none, which is why the Tribune found only 465 guaranteed jobs across 53 deals.

Frequently Asked Questions

Can a Texas school district give a data center a tax abatement?

No. The Comptroller states that school districts may not enter into Chapter 312 abatement agreements. Their main remaining tool, JETI, does not list data centers among its eligible project types.

How long can a Chapter 312 abatement last?

Up to 10 years. Only the increase in value over the January 1 value in the year of signing can be abated. Chapter 380 and 381 agreements have no required end date.

How much local tax have Texas data centers received?

At least $1 billion across 53 agreements covering 34 data centers, according to a November 2026 Texas Tribune analysis of Comptroller data. The Tribune said the true total is likely higher.

Does rejecting an abatement stop a data center?

Usually not. Brazoria County officials said Nightpeak’s project would likely proceed after they denied its abatements, because Texas counties have limited land-use authority.

Sources and Further Reading

  1. Texas cities and counties forgo $1 billion in local taxes to data centers in exchange for minimal job guarantees (The Texas Tribune, via High Plains Public Radio)
  2. About Tax Abatements, Chapter 312 (Texas Comptroller of Public Accounts)
  3. Texas Jobs, Energy, Technology and Innovation (JETI) program (Office of the Texas Governor)
  4. JETI program article, Fiscal Notes (Texas Comptroller of Public Accounts)
  5. JETI Frequently Asked Questions (Texas Comptroller of Public Accounts)
  6. House Bill 5, 88th Legislature, enrolled text (Texas Legislature)
  7. Guadalupe County commissioners vote down $500M tax cut for proposed data center in New Braunfels (Community Impact)
  8. Cloudburst secures tax breaks for Central Texas data center (The Real Deal)
  9. Houston-area county rejects tax break for $3.5B data center project (Bisnow)
  10. Texas county blocks tax break for SpaceX data center (Newsweek)
  11. Fort Worth delays tax incentives for $1B-plus data center (The Real Deal)
  12. As Fort Worth prepares to hold robust discussions on growing data centers, residents rally together (KERA News)
  13. Texas county uses tax incentives to steer data center development (RFD-TV)
  14. RELLIS Data and Research Center gets fresh start as Bryan approves replacement tax agreement (KBTX)
  15. Brazos County commissioners approve new owner for RELLIS data center (KBTX)
  16. Iola ISD to discuss SpaceX-linked JETI proposal at board meeting (KBTX)