Meta's El Paso AI data center is now a $14B, 1 GW campus owned 80% by BlackRock funds. See jobs, incentives, El Paso Electric's gas plant and water use.

Quick Answer: Meta’s AI data center in far Northeast El Paso has grown from a $1.5 billion first phase announced in October 2025 into a 1-gigawatt campus with about $14 billion in total development cost, now owned 80% by BlackRock-managed funds and 20% by Meta, which leases the whole site. More than 2,300 workers were on site by July 2026, and capacity is expected to start coming online in 2028. El Paso Electric’s proposed 366 MW gas plant to power it is awaiting a state decision.

El Paso is now home to a 1-gigawatt AI campus. Meta broke ground on its El Paso data center in October 2025, expanded the plan in March 2026 and, in July 2026, brought in BlackRock as majority owner through a new venture. Because El Paso sits on the Western Interconnection rather than the ERCOT grid, the project is also testing a different power model from most Texas data centers: a regulated utility, El Paso Electric, building generation specifically for one customer. This report covers the investment, the site, the jobs, the incentives, the power plan and the water arrangements.

How big is Meta’s El Paso data center?

Meta announced the groundbreaking on October 15, 2025, describing the facility as its 29th data center and its third in Texas, designed to scale to 1 gigawatt (GW). The initial investment was more than $1.5 billion for the first phase. On March 26, 2026, Meta updated the plan, saying the campus would officially grow to 1 GW and raising its investment to more than $10 billion. Meta first committed $800 million to El Paso in late 2023.

In July 2026, Meta announced a strategic venture with BlackRock that puts the total development cost at about $14 billion, covering the buildings and the long-lived power, cooling and connectivity infrastructure.

How Meta’s El Paso Project Has Grown
Measure October 2025 March 2026 July 2026
Investment More than $1.5B (first phase) More than $10B About $14B total development cost
Peak construction workers About 1,800 More than 4,000 More than 4,000 (2,300+ on site)
Operational jobs About 100 More than 300 More than 300
Capacity Designed to scale to 1 GW 1 GW 1 GW

Source: Meta Newsroom announcements.

Where is the site?

The data center sits on a 1,000-acre parcel in far Northeast El Paso near the Texas-New Mexico state line, between Stan Roberts Sr. Avenue and State Line Road, El Paso Matters reported. The Real Deal, citing a state construction filing, reported that the project has five phases. Phase 1 covers 600 acres with 12 buildings and five owner substations, carries a filed cost of $289 million and is expected to be finished in February 2029. The Real Deal also reported the internal code name Project Seafox. The filed Phase 1 cost appears to cover a portion of building construction rather than the full investment.

The city’s December 2023 agreement was signed with Wurldwide LLC, a Meta affiliate, and the project was developed in collaboration with The Borderplex Alliance, the region’s economic development organization.

How does the BlackRock venture work?

Under the July 2026 venture, funds managed by BlackRock own 80% of the El Paso campus and Meta owns 20%. According to Meta, BlackRock contributes about $4.9 billion in cash, funded in part by $12.5 billion of debt financing. Meta contributes land and construction-in-progress assets valued at about $2.3 billion and receives a one-time distribution of about $1 billion.

Meta will lease the entire campus. The initial lease term is four years, with four extension options that could bring the total to 20 years. The venture expects to begin bringing capacity online in 2028.

Meta-BlackRock El Paso Venture
Total development cost About $14 billion
Ownership 80% BlackRock-managed funds; 20% Meta
BlackRock cash contribution About $4.9 billion
Debt financing $12.5 billion
Meta contribution Land and construction-in-progress, about $2.3 billion
One-time distribution to Meta About $1 billion
Lease Meta leases entire campus; 4-year initial term, up to 20 years with options
First capacity Expected in 2028

The structure lets Meta use the full 1 GW campus through a long-term lease while outside investors fund most of the capital cost. For the El Paso market, it also means the project’s financing is now committed at a scale well beyond the original first phase.

How many jobs will the data center create?

Meta’s original plan called for about 1,800 construction workers at peak and about 100 operational jobs for the first phase. After the March 2026 expansion, Meta raised those figures to more than 4,000 construction workers at peak and more than 300 operational jobs. In its July 2026 announcement, Meta said more than 2,300 workers were already on site. The city agreements require 50 full-time jobs, a minimum well below Meta’s current projection.

Meta has also tied the project to workforce programs. The site is part of America’s Workforce Academy, a free skilled-trades training program, and Meta gave El Paso public schools a $500,000 grant.

What incentives did El Paso offer?

The City of El Paso approved an abatement of 80% of city property taxes on the project. Published accounts of the term differ: El Paso Matters reported an 80% abatement over 35 years, while the Texas Tribune and Inside Climate News reported an abatement of up to 80% for 15 years. According to the Texas Tribune’s account, the abatement applies if Meta invests $800 million, and the El Paso Times reported that the incentives could be worth up to $110 million. El Paso County also offered an abatement.

The city is also providing $12.5 million for roads near the site. That money comes from a Texas economic development fund created from El Paso Electric’s $80 million, 15-year payment tied to approval of the utility’s 2020 acquisition, El Paso Matters reported. The agreement states that Meta is not obligated to pursue alternative energy sources such as solar.

How will the data center get power?

El Paso Electric (EPE), the regulated utility serving the city, created a special rate for the data center. EPE says the rate reflects the full cost of service and is not a discount. Before the rates were finalized in August 2025, Public Utility Commission of Texas Commissioner Courtney Hjaltman raised concerns about possible subsidies, and EPE put in writing that its next rate case would show Meta is not being subsidized by other customers. At full operation, Meta would be EPE’s largest retail customer. Meta paid for the new transmission lines and substations needed to connect the site and says the site’s electricity use will be matched with 100% clean and renewable energy.

What is the McCloud gas plant?

EPE initially said Meta’s power would come from solar, then applied to the PUCT for a certificate to build the McCloud plant, a 366 MW natural gas facility. According to Inside Climate News, the plant would use 813 modular gas generators of 450 kilowatts each supplied by Enchanted Rock, at an estimated cost of $499 million. For its first five years the plant would serve only the data center, with Meta paying all costs, after which it could join EPE’s broader system. EPE’s filing said enough solar and storage to serve the load would require thousands of acres next to the site, land that is not available. The target operating date was 2027 if approved.

The City of El Paso intervened in the case to press for ratepayer protections. The State Office of Administrative Hearings held hearings on July 8 and 9, 2026. City Attorney Karla Nieman said the city’s priority was protecting El Paso ratepayers. In a proposal for decision issued around September 23, 2026, the administrative law judges found that EPE had not issued a request for proposals or performed a cost-benefit analysis, and recommended approving the plant only if ratepayers are charged none of its capital or operating costs, and denying it otherwise. The Texas Commission on Environmental Quality has already issued the plant’s air permit. A final PUCT decision had not been confirmed in the sources reviewed for this report.

El Paso Electric McCloud Plant
Capacity 366 MW
Equipment 813 modular gas generators of 450 kW (Enchanted Rock)
Estimated cost $499 million
Cost responsibility Meta pays all costs for first five years
Air permit Issued by TCEQ
Hearing July 8-9, 2026 (SOAH)
Proposal for decision About Sept. 23, 2026: approve only with no ratepayer costs
PUCT decision Pending as of latest reports

Why is El Paso different from the ERCOT market?

El Paso is on the Western Interconnection, not the ERCOT grid, which is why a Texas utility can build and own generation for a specific customer there. Inside Climate News noted that ERCOT’s August interconnection audit does not affect the Meta project. EPE’s 2024 power mix was 41.7% carbon-free, made up of 37% nuclear and 4.7% solar, and the utility has targets of 80% carbon-free power by 2035 and 100% by 2045.

How much water will the data center use?

The El Paso Water agreement allows the data center an average of 750,000 gallons per day at first, rising to 1.5 million gallons per day at full buildout, El Paso Matters reported. For comparison, the Marathon refinery averaged 1.1 million gallons per day, EPE averaged 19 million gallons per day, and El Paso Water supplies about 40 billion gallons a year.

Meta says the site uses a closed-loop liquid cooling system that requires no operational water for most of the year, and it pledges to restore 200% of the water the site consumes. El Paso Water CEO John Balliew has said use would rise only on extremely hot days. Meta also announced a $25,000 contribution to El Paso Water’s AguaCares program, which helps about 100 families, a partnership with DigDeep to bring running water to more than 100 homes, and an irrigation program with the Bonneville Environmental Foundation. Meta expects the buildings to achieve LEED Gold certification.

Are other data centers coming to the El Paso region?

Across the state line, Project Jupiter, an OpenAI and Oracle campus in Santa Teresa in Doña Ana County, New Mexico, was approved on September 19, 2025, El Paso Matters reported. Its developers say it will use 20,000 gallons of water a day and build its own natural gas plant. In El Paso, Ferveret, a liquid-cooling startup, received $875,000 in city incentives and plans 30 jobs at the Innovation Factory at El Paso International Airport.

What should the Texas data center industry watch?

  • The PUCT ruling on McCloud. Whether the commission follows the judges’ recommendation will set the terms for utility-built generation serving a single data center customer.
  • First capacity in 2028. The venture’s timeline and the February 2029 Phase 1 completion date in the state filing will show how quickly the campus ramps.
  • EPE’s next rate case. The utility has committed to showing Meta is not subsidized by other customers.
  • Water use. Actual consumption compared with the 750,000 gallons per day initially allowed.
  • Financing models. The 80/20 BlackRock structure, with $12.5 billion of debt, is a financing structure other Texas hyperscale projects will be measured against.

Frequently Asked Questions

How much is Meta investing in El Paso?

Meta raised its investment to more than $10 billion in March 2026, and the July 2026 BlackRock venture puts total development cost at about $14 billion.

Who owns the El Paso data center?

Funds managed by BlackRock own 80% and Meta owns 20%. Meta leases the entire campus.

When will the El Paso data center open?

The venture expects capacity to start coming online in 2028; a state filing lists February 2029 for Phase 1 completion.

How many jobs will it create?

Meta projects more than 4,000 construction workers at peak and more than 300 operational jobs.

Is the El Paso data center on the ERCOT grid?

No. El Paso is on the Western Interconnection and is served by El Paso Electric, which has proposed the 366 MW McCloud gas plant to supply it.

Sources and Further Reading

  1. Breaking Ground on Our New AI-Optimized Data Center in El Paso – Meta Newsroom
  2. Meta Announces New Strategic Venture With BlackRock to Develop Data Center in El Paso – Meta Newsroom
  3. Meta to Build $1.5 Billion Data Center in Northeast El Paso – El Paso Matters / Texas Standard
  4. El Paso’s Plan to Build Natural Gas Power Plant for Massive Data Center Kicks Up Opposition – Inside Climate News / Texas Tribune
  5. City Continues Advocacy for Ratepayer Protections as McCloud Generation Case Heads to Hearing – City of El Paso
  6. Texas Electric Utility Only Considered Gas to Power $10 Billion Meta Data Center – Inside Climate News
  7. Meta Plans $10B El Paso Data Center Campus – The Real Deal