Quick Answer: Texas bitcoin miners are turning their power-rich sites into AI data centers. Riot Platforms signed a 15-year, 910-megawatt lease at Corsicana worth about $28 billion over its initial term, Core Scientific is converting its Pecos site into a 1.5-gigawatt AI campus, Cipher Digital signed a $5.5 billion AWS lease, and IREN signed a roughly $3.4 billion Nvidia contract starting at Childress. Their biggest asset is grid capacity already secured in ERCOT.
For most of the last decade, the business model at Texas sites in Rockdale, Corsicana, Pecos, Denton and Childress was simple: secure large amounts of cheap power, fill buildings with bitcoin mining machines and sell the coins. In 2026 the same companies are signing long-term leases with technology companies and chipmakers that want somewhere to plug in AI servers. The reason is not the buildings. It is the electricity hookups, which have become the scarcest input in the data center business.
This article summarizes the largest Texas conversions announced or disclosed through November 2026, the lease terms that have been made public, how the companies are paying for the build-out and the grid policy changes that shape what comes next.
Why Are Bitcoin Miners Converting to AI Data Centers?
The Electric Reliability Council of Texas had more than 438,000 megawatts of proposed large-load demand in its connection queue as of mid-2026, with about 90% of requests coming from data centers, The Block reported in June. Against that backlog, a site that already has an energized grid connection, substations and approved power capacity can deliver computing capacity years sooner than a greenfield project.
Former mining companies hold exactly that kind of capacity. Riot Platforms, for example, has a fully approved power portfolio of 1.7 gigawatts, ForkLog reported in January 2026. Core Scientific has said it secured an additional 300 megawatts from the local utility at Pecos, according to The Register. The economics also favor the switch: a long-term lease with fixed rent and escalators produces predictable income, while mining revenue depends on the price of bitcoin.
What Has Riot Platforms Signed in Texas?
Riot has moved furthest in disclosing lease terms. HackerNoon, citing an exhibit filed with the Securities and Exchange Commission, reported in November 2026 that Riot has 1,151 megawatts of contracted data center capacity and about $38 billion in long-term revenue commitments across its Texas sites.
| Riot lease | Site | Capacity | Term | Value reported |
|---|---|---|---|---|
| Hyperscale tenant lease | Corsicana | 910 MW critical IT | 15 years, plus two 5-year extensions | About $28 billion initial term; about $54 billion with extensions |
| Frontier AI lab lease (tenant unnamed) | Rockdale | 191 MW | 20-year initial term | About $9.1 billion; up to $16.1 billion with extensions |
| AMD lease, first phase | Rockdale | 25 MW delivered | 10-year initial term | About $311 million |
| AMD lease, second phase | Rockdale | 25 MW (10 MW Nov. 2026, 15 MW May 2027) | Not stated | About $325 million |
Source: HackerNoon, November 13, 2026, citing Riot’s SEC filings. AMD also holds options on up to another 150 MW.
How much rent will Riot’s Corsicana lease generate?
The Corsicana lease is triple-net, with base rent of $130 per kilowatt per month and a 3% annual escalator, according to HackerNoon. The tenant pays for the full contracted capacity regardless of use. At full capacity, annual rent is about $1.8 billion. Delivery is scheduled in three stages: 400 megawatts in September 2027, 200 megawatts in January 2028 and 310 megawatts in July 2028, according to a KuCoin research summary.
The capital cost is also large. HackerNoon reported total Corsicana capital spending of about $5.5 billion, including about $1.8 billion from Riot, roughly $2 million per megawatt, for site and electrical work, and about $3.6 billion in reimbursements to the tenant for modules, at up to $4 million per megawatt. Riot’s primary financing plan is non-recourse project debt, with tenant funding offset by rent credits as a fallback.
Is Riot still mining bitcoin?
Yes, but it is selling coins to fund the transition. Riot sold a record 1,080 bitcoin in December 2025, more than double the 460 it mined that month, ForkLog reported. HackerNoon reported Riot sold 10,599 bitcoin in the third quarter of 2026 and 20,264 year to date, about $1.5 billion, leaving 2,418 bitcoin on hand at September 30. In the third quarter, mining still produced most of Riot’s revenue: $116 million of $181.4 million, compared with $18.4 million from data centers and $47 million from engineering.
Riot also bought its Rockdale site outright. ForkLog reported in January 2026 that the company paid $96 million in cash for an approximately 81-hectare plot it previously leased, gaining fee-simple ownership.
What Is a Megawatt of AI Capacity Worth in Texas?
The disclosed lease values make it possible to estimate what tenants are paying per megawatt. The figures below divide each reported contract value by its capacity and initial term. They are simple averages that ignore escalators and timing, so they are best used for comparison rather than valuation.
| Lease | Reported value | Capacity | Initial term | Average value per MW per year (calculated) |
|---|---|---|---|---|
| Riot Corsicana | About $28 billion | 910 MW | 15 years | About $2.05 million |
| Riot Rockdale, frontier AI lab | About $9.1 billion | 191 MW | 20 years | About $2.38 million |
| Riot Rockdale, AMD first phase | About $311 million | 25 MW | 10 years | About $1.24 million |
The Corsicana figure lines up with the lease’s disclosed base rent. At $130 per kilowatt per month, a megawatt earns about $1.56 million a year in the first year; with a 3% annual escalator over 15 years, the average rises above $1.9 million, close to the $2.05 million implied by the $28 billion headline. The higher per-megawatt figure for the Rockdale AI lab lease suggests either a higher rate or a longer escalation runway over its 20-year term, while the AMD lease, a smaller and earlier deal, is priced well below both.
What does it cost to build?
Corsicana’s total capital cost of about $5.5 billion works out to roughly $6 million per megawatt of critical IT capacity, calculated from the HackerNoon figures. Riot’s share, about $2 million per megawatt, covers site and electrical work, while the tenant-side modules cost up to $4 million per megawatt. Against annual rent of about $1.8 billion at full capacity, the total project cost equals roughly three years of rent, before operating costs and financing.
What Is Core Scientific Building in Pecos and Denton?
Core Scientific announced in April 2026 that it is converting a 300-megawatt bitcoin mining operation in Pecos into a 1.5-gigawatt AI data center campus, The Register reported. Construction began earlier in 2026, with the first new data hall expected in early 2027 and about 1 gigawatt of leasable capacity on completion. The company plans a scalable behind-the-meter power solution in addition to the 300 megawatts it secured from the local utility.
Core Scientific’s Denton facility is already serving AI customers. CoreWeave has contracted for capacity there, and ForkLog, citing The Information, reported that CoreWeave deployed 16,000 GPUs at Denton for OpenAI, with an estimated investment of about $6.1 billion.
| Core Scientific metric | Figure |
|---|---|
| Pecos conversion | 300 MW mining site to 1.5 GW AI campus |
| Pecos leasable capacity on completion | About 1 GW |
| First Pecos data hall | Expected early 2027 |
| Billing capacity, September 30, 2026 | 485 MW |
| Q1 2026 colocation revenue | $78 million |
| Q3 2026 colocation revenue | $215.4 million of $232.9 million total |
| Planned junk bond sale (April 2026) | $3.3 billion |
Sources: The Register, April 27, 2026; The Block, June 18, 2026; KuCoin research summary, November 18, 2026.
The revenue figures show how quickly the business has changed. In the first quarter of 2026, colocation revenue of $78 million was more than double Core Scientific’s bitcoin mining revenue, according to The Block. By the third quarter, colocation accounted for $215.4 million, or about 92%, of total revenue.
What Deals Have Cipher, IREN and CleanSpark Made?
Cipher Digital
Cipher Digital signed a $5.5 billion lease with Amazon Web Services at its Black Pearl campus in Texas, The Block reported, following an earlier Barber Lake deal of about $3 billion backed by a Google guarantee. Phased delivery of high-performance computing capacity at Black Pearl began in August 2026. A September 2026 amendment to the Barber Lake agreement makes Cipher responsible for the first $359.3 million of cost overruns, with the tenant reimbursing 50% of further excess costs subject to conditions.
IREN
IREN signed a five-year AI cloud contract with Nvidia worth about $3.4 billion in May 2026, starting with about 60 megawatts at its Childress, Texas campus. The partnership targets up to 5 gigawatts over time, and Nvidia holds a conditional right to buy up to 30 million IREN shares at $70 each. IREN has about $15 billion in planned fiscal 2027 capital spending, with about $9 billion funded.
CleanSpark
CleanSpark signed a definitive agreement to buy 447 acres in Brazoria County for a planned 300-megawatt data center designed for AI and high-performance computing, expandable to 600 megawatts, Cointelegraph reported. The deal was expected to close in the first quarter of 2026.
| Company | Texas site(s) | Capacity or deal | Customer |
|---|---|---|---|
| Riot Platforms | Corsicana, Rockdale | 1,151 MW contracted; ~$38B commitments | Hyperscale tenant, frontier AI lab, AMD |
| Core Scientific | Pecos, Denton | 1.5 GW Pecos campus; 485 MW billing | CoreWeave and others |
| Cipher Digital | Black Pearl, Barber Lake | $5.5B lease; ~$3B lease | AWS; Google-backed tenant |
| IREN | Childress | ~60 MW initial; up to 5 GW target | Nvidia (~$3.4B contract) |
| CleanSpark | Brazoria County | 300 MW, expandable to 600 MW | Not disclosed |
How Is Texas Grid Policy Affecting the Pivot?
In June 2026, the Public Utility Commission of Texas approved ERCOT’s “Batch Zero” process for allocating grid capacity to large loads, under which projects are evaluated in batches rather than one at a time, The Block reported. The publication said the framework could benefit former miners whose capacity is already contracted.
Scrutiny has since increased. ERCOT’s preliminary update on November 5, 2026, covered community-impact questionnaires for 465 large loads, with 433 responses representing about 177 gigawatts of requested connection capacity, not approved capacity, according to the KuCoin summary. ERCOT’s review report is targeted for December 10, 2026. Some large-load energization approvals were temporarily paused during the review, the summary said.
For companies with energized, approved capacity, a tighter review process for new requests can raise the value of what they already hold. For companies still counting on future interconnection approvals, it adds timing risk.
What Are the Risks for Texas Miner-Turned-Data-Center Operators?
- Construction cost and schedule: Cipher’s agreement to absorb the first $359.3 million of overruns at Barber Lake shows how much risk can sit with the developer.
- Financing: Riot’s Corsicana plan relies primarily on non-recourse project debt, Core Scientific planned a $3.3 billion bond sale, and IREN has about $6 billion of planned capital spending still to fund.
- Cash flow during the transition: Riot reported operating cash flow of negative $214.3 million in the third quarter of 2026 while it builds, according to HackerNoon.
- Grid timing: ERCOT’s large-load review and any pauses in energization approvals could affect delivery dates for capacity not yet energized.
Frequently Asked Questions
Which Texas bitcoin miners are becoming AI data centers?
Riot Platforms (Corsicana and Rockdale), Core Scientific (Pecos and Denton), Cipher Digital (Black Pearl and Barber Lake), IREN (Childress) and CleanSpark (Brazoria County) have all announced AI or high-performance computing projects in Texas.
How big is Riot’s Corsicana data center lease?
The 15-year lease covers 910 megawatts of critical IT capacity and is worth about $28 billion over its initial term, or about $54 billion with two five-year extensions.
Why do AI companies want former bitcoin mining sites?
The sites already have large grid connections and approved power capacity. With more than 438 gigawatts of proposed large loads in ERCOT’s queue, existing capacity can deliver computing years sooner than new sites.
Is Core Scientific still a bitcoin miner?
Mostly not by revenue. Colocation produced $215.4 million of its $232.9 million in third-quarter 2026 revenue.
What is ERCOT’s Batch Zero?
It is a process, approved by the PUCT in June 2026, for allocating grid capacity to large loads in batches rather than one project at a time.
Sources and Further Reading
- Core Scientific accelerates crypto-to-AI pivot, The Register
- New Texas power grid allocation framework could lift bitcoin miners turned data center operators, The Block
- Riot Platforms sells 1,080 BTC to expand in AI, ForkLog
- Riot Platforms is turning its bitcoin mining empire into AI infrastructure, HackerNoon
- CleanSpark mining AI and HPC Texas acquisition, Cointelegraph
- Nvidia turmoil and Texas permit restrictions test bitcoin miners’ AI pivot, KuCoin research blog